Barriere demolished and reconstructed a defunct electrical substation in New Orleans. The substation sat on a compact 350’x350’ footprint and was sandwiched by Interstate 10, an active railroad, and a city neighborhood. Crews demolished the “Steel Spider Web” piece by piece and broke up the pavement.

The team drove (520) 60’ timber and (21) 70’ precast concrete piles to support the foundation for a prefabricated control house and constructed 170 concrete foundations for the new electrical structures. Barriere also installed a 1000’ duct bank 9’ deep as part of the power distribution infrastructure and a 708’ concrete retaining wall on 3 sides of the property to contain the fill required to achieve the required finished grade.

Awards

ABC Bayou – Excellence in Construction
GNOBR
ENR

Related Projects

Entergy Superdome Vault

Entergy Superdome Vault

Client

Entergy

Value

$400,000

Entergy Horseshoe Substation

Entergy Horseshoe Substation

Client

Entergy

Value

$2.1M

Entergy Schriever Substation

Entergy Schriever Substation

Client

Entergy

Value

$2.4M

SUBSCRIBE TO THE NEWSLETTER

Stay informed about company news and construction industry trends and insights.

lapa
agcoa
gbria
abcinc
napa
napa
logo-on-dark-gray