IMT YARD EXPANSION PHASE 3A

Client: Kinder Morgan
Location: Port Sulphur, LA
Completion Date: Feb. 2014
Value: $6.9 million
Man Hours: 45,668
Materials Used:
- 1593 cy of Structural Concrete
- 404,000 lbs of Rebar
- 3,600 sq. yards of area paving
- 50,900 cyt of excavation
- 39,000 cyt of fill
- 33,000 sq. yards of soil cement
- 24,100 tons of rock
Awards:
ABC Bayou
ABC Pelican
GNOBR

THE PROJECT

Barriere increased the facility’s capacity and efficiency by installing concrete foundations and 25’ walls with soil cement pads and constructing a electrical duct bank and dust suppression piping. Because of the team’s quality work and innovation, Kinder Morgan added $2.2 million of work to re-engineer and reconstruct the berms from future phases done by other contractors.